Is there any documentation available for following dates calculation( Rollup logic, Past date /Future date validations) on Project and Project task form
1) Planned Start date
2) Planned End date
3) Actual Start date
4) Actual End date
Solved! Go to Solution.
02-25-2019 01:55 PM
Thanks Sachin.
I found one more article from the same person and that answered my 80% of question.
This is for Geneva version.
https://community.servicenow.com/community?id=community_question&sys_id=e719c7e1db5cdbc01dcaf3231f961942
02-25-2019 12:27 PM
Please see below useful log related to project dates and calculations
https://community.servicenow.com/community?id=community_question&sys_id=142017e5dbdcdbc01dcaf3231f96198d
Regards,
Sachin
02-25-2019 12:50 PM
Thanks Sachin for sharing the link. I think this documentation is not applicable for Jakarta or above version.
And What I am looking for is more Roll up and Validation of the dates between Project and Project task.
02-25-2019 01:47 PM
Please check below for roll up calculations between project and project task for London release.
https://docs.servicenow.com/bundle/london-it-business-management/page/product/project-management/concept/c_ParentChildRollupTaskCalcs.html
Regards,
Sachin
02-25-2019 01:55 PM
Thanks Sachin.
I found one more article from the same person and that answered my 80% of question.
This is for Geneva version.
https://community.servicenow.com/community?id=community_question&sys_id=e719c7e1db5cdbc01dcaf3231f961942