Documentation - Project Management dates ( Planned start date , Planned End Date , Actual Start Date ) calculation and validation

Saurabh Kumar2
Giga Expert

Is there any documentation available for following dates calculation( Rollup logic, Past date /Future date validations) on Project and Project task form

1) Planned Start date

2) Planned End date

3) Actual Start date

4) Actual End date

1 ACCEPTED SOLUTION

Thanks Sachin.

I found one more article from the same person and that answered my 80% of question.

This is for Geneva version.

https://community.servicenow.com/community?id=community_question&sys_id=e719c7e1db5cdbc01dcaf3231f961942

View solution in original post

4 REPLIES 4

sachin_namjoshi
Kilo Patron
Kilo Patron

Please see below useful log related to project dates and calculations

 

https://community.servicenow.com/community?id=community_question&sys_id=142017e5dbdcdbc01dcaf3231f96198d

 

Regards,

Sachin

 

 

Thanks Sachin for sharing the link. I think this documentation is not applicable for Jakarta or above version.

And What I am looking for is more Roll up and Validation of the dates  between Project and Project task.

 

Please check below for roll up calculations between project and project task for London release.

 

https://docs.servicenow.com/bundle/london-it-business-management/page/product/project-management/concept/c_ParentChildRollupTaskCalcs.html

 

Regards,

Sachin

Thanks Sachin.

I found one more article from the same person and that answered my 80% of question.

This is for Geneva version.

https://community.servicenow.com/community?id=community_question&sys_id=e719c7e1db5cdbc01dcaf3231f961942