how Estimate to completion and estimate at completion field are calculated on cost plan?
Solved! Go to Solution.
‎10-21-2019 07:02 PM
Estimate at Completion | Sum of all actuals from breakdowns of past fiscal periods added to the functional cost for future fiscal periods.
For example, the duration of a cost plan is from FY19 M01 to FY19 M12, and if you check the Estimate at Completion in the month of May, it is calculated as: |
Estimate to completion | is calculated by aggregating the functional cost on the breakdowns of current and future fiscal periods |
‎10-21-2019 07:02 PM
Estimate at Completion | Sum of all actuals from breakdowns of past fiscal periods added to the functional cost for future fiscal periods.
For example, the duration of a cost plan is from FY19 M01 to FY19 M12, and if you check the Estimate at Completion in the month of May, it is calculated as: |
Estimate to completion | is calculated by aggregating the functional cost on the breakdowns of current and future fiscal periods |